鐵路電氣化改造中上跨橋梁的頂升(50 卷) |
英文標(biāo)題 |
Lifting of bridge due to reconstruction of railway electrification |
摘要 |
在非電氣化鐵路進(jìn)行電氣化改造施工中,主要難題之一就是鐵路上跨橋梁凈空不足,導(dǎo)致接觸網(wǎng)安全距離不夠,需將原有橋梁拆除重建。在電氣化改造引起的上跨橋梁改建施工中,將拆除重建方案改為既有橋頂升方案,并進(jìn)行了分析和檢算,較好地解決了電氣化改造中橋梁凈空不足的難題 |